File #: 24-0243    Version: 1
Type: Item(s) for Discussion
In control: Council Audit Committee
Final action:
Title: ACCEPT BY MOTION PROPOSITION 111 APPROPRIATION LIMIT (GANN LIMIT), CORE REVENUES AUDIT, MEASURE M STRONG COMMUNITIES TAX FUND AUDIT, AND MEASURE W PUBLIC SAFETY TAX FUND AUDIT FOR THE YEAR ENDED JUNE 30, 2023
Attachments: 1. Attachment A - 2023_Stockton City of_GANN_DRAFT_02122024_SC, 2. Attachment B - 2023_Stockton City of_Core Revenue AUP_FINAL DRAFT_03032024_CM, 3. Attachment C - 2023_Stockton City of_Measure M_DRAFT_02122024_SC, 4. Attachment D - 2023_Stockton City of_Measure W_DRAFT_01122024_SC

title

ACCEPT BY MOTION PROPOSITION 111 APPROPRIATION LIMIT (GANN LIMIT), CORE REVENUES AUDIT, MEASURE M STRONG COMMUNITIES TAX FUND AUDIT, AND MEASURE W PUBLIC SAFETY TAX FUND AUDIT FOR THE YEAR ENDED JUNE 30, 2023

 

recommended action

RECOMMENDATION

 

It is recommended that the Audit Committee accept by motion the Proposition 111 Appropriation Limit (GANN Limit) Agreed-Upon Procedures Report, the Agreed-Upon Procedures Applied to Core Revenues Report, the Measure M Strong Communities Tax Fund Audit, and the Measure W Public Safety Tax Fund Audit for the year ended

June 30, 2023, for submission to the City Council.

 

body

Summary

 

Presented for the Audit Committee’s review and acceptance are the City of Stockton’s:

 

                     Agreed-Upon Procedures Report on Compliance with Proposition 111 Appropriation Limit (GANN Limit) for the year ended June 30, 2023

(Attachment A).  The City met the requirements of the Gann Limit Calculation, Article XIII-B of the California Constitution, and the auditors found no exceptions.

                     Independent Accountants’ Report of Agreed-Upon Procedures Applied to Core Revenues (Attachment B).  The Agreed-Upon Procedures engagement was conducted in accordance with attestation standards established by the American Institute of Certified Public Accountants.  The auditors found no exceptions.

                     Measure M Strong Communities Tax Fund Audit (Measure M) for the year ended June 30, 2023 (Attachment C).  The City received an unmodified (clean) opinion.

                     Measure W Public Safety Tax Fund Audit (Measure W) on a comparative basis for the year ended June 30, 2023 (Attachment D).  The City received an unmodified (clean) opinion.

 

Once accepted, these reports will be submitted to the City Council for acceptance at its March 19, 2024, meeting. 

 

DISCUSSION

 

Proposition 111 or Gann Limit Report

 

State law limits appropriations made by the State and individual local governments.  The limit for the growth rate of those appropriations is the percentage increase in the cost of living and the percentage increase in the State or local government's population.  Each year City staff calculates the appropriation limit.  The procedures performed by the auditor were to test the sufficiency of the procedures the City used to determine the Proposition 111 appropriation limit for fiscal year 2022-23.  The auditors did not discover any findings from the application of these audit procedures.

 

Agreed-Upon Procedures Applied to Core Revenues

 

The procedures performed on the City’s Core Revenues Schedule for the year ended June 30, 2023, meet the annual requirements under the Reimbursement Agreement between the City and Assured Guaranty Municipal Corporation, as stipulated in Article IV Covenants, Section 4.02(b).  This Agreement entitled: “Agreed-Upon Procedures Applied to the Core Revenues,” is part of the City’s approved Bankruptcy Plan of Adjustment.  The Plan wrote-down the liabilities of the Taxable Pension Obligation Bonds 2007 Series A and B and non-taxable Variable Rate Bonds Series 2007 A and B for property on Main Street. 

 

This negotiated Agreement created an alternate liability and related payments that began on February 25, 2015.  As part of the Agreement, the City agreed to make contingent General Fund payments commencing on June 1, 2018, through

June 1, 2052, in the manner described in Section 2.05 of the Agreement.  The calculation of potential contingent General Fund payments is made by determining actual core revenues over baseline core revenue and averaging revenue increments of three fiscal years.  The City is obligated to pay an allocable share of resulting incremental revenue to Assured Guaranty Municipal Corporation subject to the provisions of subsections (c) and (d) of Section 2.03.  The City’s Long-Range Financial Plan anticipates future contingent payments from the General Fund.  The actual payments depend on future revenue receipts, but the payments are estimated to be approximately $3.3 million annually for the first ten years.

 

Measure M Strong Communities Tax Fund

 

Measure M, approved by voters on November 8, 2016, authorized Ordinance No.

2016-06-07-1212 that provides for an additional one-quarter cent sales tax with proceeds to be used exclusively for library and recreation services.  The City separately accounts for Measure M revenues and related expenditures.  The measure requires an annual audit, which was conducted for the fiscal year ending June 30, 2023.  The auditors did not report any findings, and the City received an unmodified (clean) opinion on the financial schedule of revenues, expenditures, and changes in fund balances of the Measure M Fund for the year ended June 30, 2023.

 

Measure W Public Safety Tax Fund

 

Measure W, approved by voters on November 2, 2004, authorized Ordinance No.

038-04 CS that provides for an additional one-quarter cent sales tax, the proceeds of which are used exclusively for police and fire services.  The Measure W Fund is where the City separately accounts for the collection of revenues generated from this sales tax and the expenditures of these taxes.  The measure approved by voters also requires an annual audit.  The auditors did not report any findings, and the City received an unmodified (clean) opinion on the financial schedule of revenues, expenditures, and changes in fund balances of the Measure W Fund for the year ended June 30, 2023.

 

 

FINANCIAL SUMMARY

 

There is no financial impact associated with accepting these items.

 

 

Attachment A - 2023 Proposition 111 Appropriation Limit (GANN Limit)

Attachment B - 2023 Independent Accountants’ Report of Agreed-Upon Procedures Applied to Core Revenues

Attachment C - 2023 Measure M Strong Communities Tax Fund Audit

Attachment D - 2023 Measure W Public Safety Tax Fund Audit