title

ADOPT A RESOLUTION APPROVING A FINAL MAP AND SUBDIVISION AGREEMENT FOR THE WESTLAKE VILLAGES, UNIT NO. 15 - VILLAGE I (TRACT NO. 3589) PROJECT

 

recommended action

RECOMMENDATION

 

It is recommended that the City Council adopt a resolution to:

 

1.                     Approve the final map for Westlake Villages, Unit No. 15 - Village I, Tract No. 3589;

 

2.                     Authorize the City Manager to execute the subdivision agreement, accept on behalf of the public all offers of dedication, and record the final map for Westlake Villages, Unit No. 15 - Village I, Tract No. 3589; and

 

3.                     Authorize the City Manager to take appropriate and necessary actions to carry out the purpose and intent of the resolution.

 

body

Summary

 

The proposed resolution approves the final map and authorizes the City Manager to execute the Subdivision Agreement between KL LB BUY 1 LLC, accept all offers of dedication, and recordation of the map for Westlake Villages Unit No. 15 - Village I, Tract No. 3589. The subdivision contains 20.75 acres divided into 88 lots for the construction of single-family residential homes, four non-residential lots and right-of-way dedication.

 

Review and approval of the Final Map and Subdivision Agreement are necessary to ensure the conditions of the Development Agreement and Tentative Map have been fulfilled. If the final map is approved by the City Council, the City will transmit the map and Subdivision Agreement to the County Recorder for recordation.

 

It is recommended that Council adopt the proposed resolution as KL LB BUY 1 LLC has fulfilled all necessary conditions.

 

DISCUSSION

 

Background

 

On September 14, 2004, the City Council approved development applications for Spanos Family Partnership for an approximate 681-acre project site located south of Eight Mile Road, west of Spanos Park West and Interstate 5, north of Pixley and Disappointment Sloughs, and east of Bishop Cut bridge and Rio Blanco Road (Attachment A - Vicinity Map). Council approvals included an Environmental Impact Report, General Plan Amendment, Development Agreement, Pre-zoning for mixed-use, Annexation application, and a Master Development Plan to facilitate a residential community consisting of 2,630 single-family residential homes, commercial space, school, parks, and fire station within a setting of man-made lakes.

 

On October 14, 2004, the City Planning Commission approved two Tentative Maps (TM 18-04 A and B) for a proposed property subdivision of the Westlake Villages Project site. Tentative Map 18-04A showed how the proposed site would be divided up into smaller parcels creating the 2,630 residential lots (792 of which were intended for an active adult community) and lots for the fire station, parks, school, landscaping, lake, and various accessory lots. Tentative Map 18-04B proposed how the site would be divided up into 30 large lots to provide the developer an opportunity to sell off larger blocks of developable land while site development is underway. The tentative maps were approved subject to specified conditions to be met upon subdivision of the project site.

 

In 2018, the City Council approved the formation of Community Facilities District (CFD) No. 2018-2 for Westlake Villages II to levy Special Taxes within the CFD to finance the construction of capital infrastructure and ongoing services related to police, fire, parks, roads, and open space.

 

Present Situation

 

KL LB BUY 1 LLC submitted a final map for Unit No. 15 - Village I to complete the subdivision process for the earlier approved Tentative Maps. The final map will subdivide an approximately 20.75-acre project site into 88 residential lots, four non-residential lots (A - D) for landscaping and utility easement and street right-of-way dedication. The residential lot sizes, ranging in size from 6,300 to 15,234 square feet, will be provided access through the project site via public streets.

 

Staff reviewed the Final Map and Subdivision applications and determined that all conditions necessary for approval have been met. This includes preparing improvement plans for all proposed public streets and utilities to be constructed within the subdivision, dedicating right-of-way easements, paying proportionate share fees towards off-site improvement costs, and posting security bonds to guarantee the subdivision improvements.

 

The City Engineer reviewed the final map for technical accuracy and substantial conformance with approved tentative maps and recommends forwarding the final map, subdivision agreement, and any offers of dedication to the City Council for consideration and approval.

 

The subdivision agreement (Exhibit 1 to the proposed resolution) contains the developer’s obligations for project site development. The proposed resolution authorizes the City Manager to execute the subdivision agreement, accept on behalf of the public all offers of dedication and authorize the recordation of the final map.

 

FINANCIAL SUMMARY

 

The costs of creating the subdivision agreement, including plan checking, inspection, map filing, and computer mapping services provided by City staff have been paid by the subdivider in the amount of $126,809.59 and deposited in various development fee accounts in the Development Services Fund and Street Sign Public Facility Fee Fund. These fees are described in detail in Exhibit A of the Agreement. All other fees will be assessed at the time building permits are issued.

 

Westlake Villages, Unit No. 15 - Village I will be incorporated into CFD No. 2018-2, which provides funding for the necessary subdivision infrastructure improvements and ongoing City services to support project development. The new fire station proposed within the Westlake Villages Development would be constructed in a future development phase when needed to address the residential demand. There is no financial impact to the City because of the execution of the subdivision agreement. The costs to construct the required infrastructure improvements and develop the subdivision are borne by the developer and addressed with the formation of the community facilities district.

 