Title: APPROVE MOTION TO AUTHORIZE CONTRACT CHANGE ORDER NO. 2 FOR THE ON-CALL PARKS PUMP REPAIRS PROJECT
Attachments: 1. Attachment A - CCO No. 2

title

APPROVE MOTION TO AUTHORIZE CONTRACT CHANGE ORDER NO. 2 FOR THE ON-CALL PARKS PUMP REPAIRS PROJECT

 

recommended action

RECOMMENDATION

 

It is recommended that the City Council approve a motion to:

 

1.                     Authorize Contract Change Order No. 2 in the amount of $60,000 with Cornerstone Environmental Contractors, Inc. of Concord, CA, for a total contract amount not to exceed $150,000, for the On-Call Parks Pump Repairs, Project No. OM-24-080.

 

2.                     Approve findings pursuant to Stockton Municipal Code section 3.68.070 in support of an exception to the competitive bidding process.

 

It is also recommended that the City Manager be authorized to take appropriate and necessary actions to carry out the purpose and intent of this motion.

 

body

Summary

 

On May 15, 2024, Public Works entered into a Service Contract in the amount of $60,000 with Cornerstone Environmental Contractors, Inc. (Cornerstone) of Concord, CA, as authorized by the City Manager, to provide on-call pump repair services to diagnose, repair, and modify well and booster pumps on Airport Way and Michael Avenue, at Laughlin and Sousa Parks, and any unanticipated repairs that will continue through the duration of the contract.

 

On December 24, 2024, Public Works executed Contract Change Order (CCO) No. 1 with Cornerstone of Concord, CA, in the amount of $30,000, to provide adequate purchasing authority due to additional repairs needed for aging equipment. 

 

It is recommended that Council approve CCO No. 2, in the amount of $60,000, with Cornerstone of Concord, CA, for the On-Call Parks Pump Repairs, Project No. OM-24-080 (Attachment A).  The total revised contract amount will be $150,000.

 

DISCUSSION

 

Background

 

The Parks Section of the Public Works Department is responsible for managing irrigation and well pump repairs at City facilities, including, but not limited to, parks, greenbelts, and street landscaped areas.  On March 12, 2024, bids were solicitated to 10 vendors. On March 25, 2024, one bid was received from Cornerstone of Concord, CA.

 

On May 15, 2024, Public Works entered into a Service Contract in the amount of $60,000 with Cornerstone, as authorized by the City Manager, to provide on-call pump repair services to diagnose, repair, and modify well and booster pumps on Airport Way and Michael Avenue, at Laughlin and Sousa Parks, and any unanticipated repairs that will continue through the duration of the contract. 

 

On December 24, 2024, Public Works executed CCO No. 1 with Cornerstone, in the amount of $30,000, to provide adequate purchasing authority due to additional repairs needed for aging equipment. 

 

On March 27, 2025, a car accident caused damage to the booster pump, backflow, bollards, and underground piping on Airport Way and Michael Avenue.  Cornerstone evaluated the damage and provided a quote for the repairs needed to restore the streetscape irrigation along Airport Way.

 

Present Situation

 

The Parks Section of the Public Works Department is responsible for managing irrigation and well pump repairs at City facilities, including, but not limited to, parks, greenbelts, and street landscaped areas.  On March 12, 2024, bids were solicitated to 10 vendors. On March 25, 2024, one bid was received from Cornerstone of Concord, CA.

 

Council approval is needed for CCO No. 2 with Cornerstone because the cumulative amount of CCO No. 2 exceeds the administrative change order authority allowed under the existing contract.  CCO No. 2 will ensure adequate funding is available for the current known repairs and for any unanticipated repairs that will continue through the duration of the contract.

 

The revised contract amount, including previously approved CCOs, will be $150,000.

It is recommended that Council approve CCO No. 2, in the amount of $60,000, with Cornerstone for the On-Call Parks Pump Repairs, Project No. OM-24-080 (Attachment A).

 

Findings

 

Pursuant to Stockton Municipal Code (SMC) section 3.68.070, Council may approve findings which support an exception to the competitive bidding process.  These findings include:

 

1.                     The City does not have the internal resources to diagnose and repair wells and booster pumps at City streetscape locations and parks. 

 

2.                     The City must continue to irrigate parks, greenbelts, and landscaped street areas. 

 

3.                     This bid was originally solicited as an informal bid, under $100,000 not requiring Council approval.  Due to the volume of damages, the contract amount will now exceed $100,000 and requires Council approval. 

 

FINANCIAL SUMMARY

 

There is sufficient funding in the Public Works Parks General Fund and Landscape Maintenance District Operating Budgets to approve CCO No. 2 with Cornerstone in the amount of $60,000. With the approval of CCO No. 2, the total revised contract amount with Cornerstone will be $150,000.

 

Attachment A - CCO No. 2 with Cornerstone