ADOPT RESOLUTION TO AUTHORIZE THE SANITARY SEWER LARGE DIAMETER SEWER LINE REHABILITATION - FISHER COURT PROJECT
recommended action
RECOMMENDATION
It is recommended that the City Council adopt a resolution to:
1. Approve Notice of Exemption No. NOE39-24 under the California Environmental Quality Act for the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020.
2. Approve the plans and specifications for the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020.
3. Award a Construction Contract in the amount of $414,903.05 to Lamassu Utility Services, Inc. of Loomis, CA, for the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020.
It is also recommended that the City Manager be authorized to take appropriate and necessary actions to carry out the purpose and intent of this resolution.
body
Summary
The Municipal Utilities Department (MUD) has implemented a Condition Assessment Program for the City’s sewer infrastructure comprised of Closed-Circuit Televised Video (CCTV) inspection, pipe cleaning, and engineering evaluation. This program generates a prioritized list of sewer replacement and/or rehabilitation projects for inclusion in the City’s Capital Improvement Plan (CIP). A 24-inch diameter sewer trunk line along Fisher Court was identified for rehabilitation. The project will rehabilitate approximately 450 linear feet of 24-inch diameter sewer trunk line along Fisher Court between Interstate 5 (I-5) and Plymouth Road (Attachment A). The project was included in the 2022-27 Five-Year CIP.
On August 21, 2025, the City received two bids for this project. It is recommended that Council award a Construction Contract to the lowest responsible bidder, Lamassu Utility Services, Inc., in the amount of $414,903.05. It is also recommended that Council adopt a resolution approving Notice of Exemption No. NOE39-24 under the California Environmental Quality Act (CEQA) and approving the plans and specifications for the project. Construction is anticipated to be completed by February 2026.
DISCUSSION
Background
MUD has implemented a Condition Assessment Program for the City’s sewer infrastructure comprised of CCTV inspection, pipe cleaning, and engineering evaluation. This program generates a prioritized list of sewer replacement and/or rehabilitation projects for inclusion in the City’s CIP. A 24-inch diameter sewer trunk line along Fisher Court was identified for rehabilitation. The project will rehabilitate approximately 450 linear feet of 24-inch diameter sewer trunk line along Fisher Court between I-5 and Plymouth Road (Attachment A). The project was included in the 2022-27 Five-Year CIP.
On July 26, 2016, Council adopted a Community Workforce and Training Agreement (CWTA). The CWTA became effective August 25, 2016, and applies to all Public Works projects over $1 million that are bid after that date. On July 16, 2019, by Motion No. 2019-07-16-1403, Council extended the CWTA term to August 25, 2024. On August 20, 2024, by Motion No. 2024-08-20-1203, Council extended the CWTA term to August 25, 2029. The CWTA was not applied to this project as the estimated construction cost was less than $1 million.
Present Situation
On July 23, 2025, the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020, was advertised for bids. On August 21, 2025, two bids were received with the following results:
COMPANY NAME BID AMOUNT
Lamassu Utility Services, Inc. (Loomis, CA) $414,903.05
Insituform Technologies, LLC (Chesterfield, MO) $750,990.00
Engineer’s Estimate $316,522.00
The requirements of Stockton Municipal Code (SMC) section 3.68.090, Local Business Preference, apply to this project. Application of the Local Business Preference has no effect on the bid order. The Local Employment Ordinance, SMC section 3.68.095, also applies to this contract.
The bid from Lamassu Utility Services, Inc., the lowest responsible bidder, is regular in all respects and has the proper license to perform the work. It is recommended that Council approve the plans and specifications, and award a Construction Contract to Lamassu Utility Services, Inc. of Loomis, CA, in the amount of $414,903.05, for the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020.
The project is in conformance with the City’s General Plan, pursuant to California Government Code, section 65402, and is statutorily exempt from the requirements of CEQA as specified under Section 15301(d) of the CEQA Guidelines. The activities related to this project constitute a discretionary project under the City’s jurisdiction and qualifies as a project that does not have a significant effect on the environment. The resolution will approve the filing of Notice of Exemption No. NOE39-24 under CEQA.
Construction is anticipated to be completed by February 2026.
FINANCIAL SUMMARY
There is sufficient funding in the Sanitary Sewer Large Diameter Sewer Line Rehabilitation - Fisher Court, Project No. UW20020, to award a Construction Contract to Lamassu Utility Services, Inc. in the amount of $414,903.05.
There is no impact to the City’s General Fund or any other unrestricted fund as a result of taking the recommended actions.