Title: ADOPT RESOLUTION TO AUTHORIZE THE STREETLIGHT KNOCKDOWN REPAIRS PHASE 7 PROJECT
Attachments: 1. Attachment A - Vicinity Map, 2. Proposed Resolution, 3. Exhibit 1 - Notice of Exemption, 4. Exhibit 2 - Construction Contract

title

ADOPT RESOLUTION TO AUTHORIZE THE STREETLIGHT KNOCKDOWN REPAIRS PHASE 7 PROJECT

 

recommended action

RECOMMENDATION

 

It is recommended that the City Council adopt a resolution to:

 

1.                     Approve Notice of Exemption No. NOE58-23 under the California Environmental Quality Act for the Streetlight Knockdown Repairs Phase 7, Project No. OM-23-016.

 

2.                     Approve the plans and specifications for the Streetlight Knockdown Repairs Phase 7, Project No. OM-23-016.

 

3.                     Award a Construction Contract in the amount of $122,723 to Ray’s Electric of Oakland, CA, for the Streetlight Knockdown Repairs Phase 7, Project No. OM-23-016.

 

It is also recommended that the City Manager be authorized to take appropriate and necessary actions to carry out the purpose and intent of this resolution.

 

body

Summary

 

Streetlight poles are installed close to the roadway and are occasionally struck by motor vehicles, resulting in toppled poles or “knockdowns.” The Streetlight Knockdown Repairs project will remove and replace five streetlight poles and four traffic signal poles that were damaged by automobile accidents at various locations citywide (Attachment A).

 

On November 9, 2023, the City received four bids for this project. Staff recommends award of the Construction Contract to the lowest responsive bidder, Ray’s Electric, in the amount of $122,723. Staff also recommends that Council adopt a resolution approving Notice of Exemption No. NOE58-23 under the California Environmental Quality Act (CEQA) and approving the plans and specifications for the project. Construction is anticipated to begin and be completed by spring 2024, weather permitting.

 

DISCUSSION

 

Background

 

The City is responsible for the operation and maintenance of approximately 19,000 streetlights. The majority of these streetlights are mounted on galvanized poles.  Streetlight poles are installed close to the roadway and are occasionally struck by motor vehicles, resulting in toppled poles or “knockdowns.” The cost to replace a foundation, pole, and fixture has increased significantly in the last five years. Depending on the severity of the damage to the foundation base and wiring, repair costs range between $5,000 and $20,000 per knockdown. The City has an average of 75 such incidents annually. The City attempts to recover damage expenses when there is a police report identifying the responsible party.

 

The Streetlight Knockdown Repairs project will remove and replace five streetlight poles and four traffic signal poles that were damaged by automobile accidents at various locations citywide (Attachment A). 

 

On July 26, 2016, Council adopted a Community Workforce and Training Agreement (CWTA). The CWTA became effective August 25, 2016, and applies to all Public Works projects over $1 million that are bid after that date.  On July 16, 2019, by Motion No. 2019-07-16-1403, Council extended the CWTA term to August 25, 2024. The CWTA was not applied to this project as the estimated construction cost is less than $1 million

 

Present Situation

 

On October 19, 2023, the Streetlight Knockdown Repairs Phase 7, Project No. OM-23-016, was advertised for bids. On November 9, 2023, four bids were received with the following results:

 

                     COMPANY NAME                                                                                                                                                            BID AMOUNT

 

                     Ray’s Electric                                                                                                                                                     $122,723

                     (Oakland, CA)

 

                     Tennyson Electric, LLC                                                                                                                                 $138,075

                     (Livermore, CA)

 

                     St. Francis Electric, LLC                                                                                                                                 $159,300

                     (San Leandro, CA)

 

                     Bear Electrical Solutions, Inc.                                                                                                            $353,500

                     (Alviso, CA)

 

                     Engineer’s Estimate                                                                                                                                                     $119,000

 

The requirements of Stockton Municipal Code (SMC) section 3.68.090, Local Business Preference, apply to this project. Application of the Local Business Preference has no effect on the bid order, as no local firms bid on the project. The Local Employment Ordinance, SMC section 3.68.095, also applies to this contract.

 

The bid from Ray’s Electric, the lowest responsive bidder, is regular in all respects and has the proper license to perform the work. Staff recommends Council approve the plans and specifications for the project and award a Construction Contract to Ray’s Electric of Oakland, CA, in the amount of $122,723.

 

 

The project is in conformance with the City’s General Plan, pursuant to California Government Code, section 65402, and is categorically exempt from the requirements of CEQA as specified under Section 15301(c) of the CEQA Guidelines. As a result, the project has been granted a Categorical Exemption. The activities related to this project constitute a discretionary project under the City’s jurisdiction and qualifies as a project that does not have a significant effect on the environment.  The resolution will approve the filing of Notice of Exemption No. NOE58-23 under CEQA. Construction is anticipated to begin and be completed by spring 2024, weather permitting.

 

FINANCIAL SUMMARY

 

There is sufficient funding in the Fiscal Year 2023-24 Electrical and Traffic Signals, Account No. 4570-717-630013-250-252-30-45-000-000, to award a Construction Contract in the amount of $122,723 to Ray’s Electric of Oakland, CA, for the Streetlight Knockdown Repairs Phase 7, Project No. OM-23-016.

 

There is no impact to the City’s General Fund or any other unrestricted fund as a result of taking the recommended actions.

 