Legislation Details

File #: 24-0764    Version: 1
Type: Consent
In control: City Council and Concurrent Authorities
Final action:
Title: ADOPT RESOLUTION TO AUTHORIZE THE LOCAL STREET RESURFACING PROGRAM FY 2023-24 SB1 - CRACK SEALING PROJECT
Attachments: 1. Attachment A - Vicinity Map, 2. Proposed Resolution, 3. Exhibit 1 - NOE29-24, 4. Exhibit 2 - Construction Contract

title

ADOPT RESOLUTION TO AUTHORIZE THE LOCAL STREET RESURFACING PROGRAM FY 2023-24 SB1 - CRACK SEALING PROJECT

 

recommended action

RECOMMENDATION

 

It is recommended that the City Council adopt a resolution to:

 

1.                     Approve Notice of Exemption No. NOE29-24 under the California Environmental Quality Act for the Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003.

 

2.                     Approve the plans and specifications for the Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003.

 

3.                     Award a Construction Contract in the amount of $286,000 to Graham Contractors, Inc. of San Jose, CA, for the Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003.

 

It is also recommended that the City Manager be authorized to take appropriate and necessary actions to carry out the purpose and intent of this resolution.

 

body

Summary

 

The project will apply crack sealing to approximately 22 centerline miles of residential, collector, and arterial roadways in various streets citywide (Attachment A).  Crack sealing involves the placement of adhesive material into pavement cracks to prevent water intrusion.  Cracks occur on the pavement due to traffic load and thermal stress, and water intrusion then weakens the pavement base structure leading to potholes and pavement failure.  Crack sealant slows the deterioration process of cracks and extends the life of the roadway from two to five years on average.  The project was included in the 2023-28 Five-Year Capital Improvement Plan (CIP).

 

On June 27, 2024, the City received six bids for this project.  Staff recommends award of the Construction Contract to the lowest responsive bidder, Graham Contractors, Inc., in the amount of $286,000.  Staff also recommends that Council adopt a resolution approving Notice of Exemption No. NOE29-24 under the California Environmental Quality Act (CEQA) and approving the plans and specifications for the project. 

 

Construction is anticipated to begin late summer 2024 and be completed by fall 2024, weather permitting.

 

 

DISCUSSION

 

Background

 

On April 28, 2017, the Governor signed Senate Bill 1 (SB1), known as the Road Repair and Accountability Act of 2017.  SB1 funding provides for basic road maintenance, rehabilitation, and critical safety needs on both the State highway and local streets and road systems.  The California Transportation Commission (CTC) is responsible for oversight of funding and/or programs created with the approval of SB1.  

 

SB1 provides funding for the Road Maintenance and Rehabilitation Account (RMRA) Program.  Other programs include the Local Partnership Program, the Active Transportation Program, State Highway Operation and Protection Program, and Local Streets and Roads Program.  The RMRA funding is part of the City’s overall Gas Tax allocation; however, RMRA funds can only be expended on projects that meet eligibility criteria and have been approved by the CTC.  RMRA funds are accounted for and reported separately from regular Gas Tax funds.

 

Approximately $7.99 million in SB1 RMRA Program funding was allocated to the City for Fiscal Year (FY) 2023-24 and approved by Council on May 2, 2023, by Resolution No. 2023-05-02-1211.  The project list was subsequently approved by the CTC and provides for multiple resurfacing projects that may consist of slurry sealing, micro-surfacing, cape seal, and/or an asphalt overlay.  These projects are all being delivered separately based on the type of resurfacing treatment.  A cost-effective method of maintaining streets is to provide treatment for streets that are in fair to good condition.  The preservation of streets in this condition is critical, as rehabilitation costs rise exponentially as pavement deteriorates.

 

The Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003, was included in the 2023-28 Five-Year CIP.  The project will apply crack sealing to approximately 22 centerline miles of residential, collector, and arterial roadways in various streets citywide (Attachment A).  Crack sealing is a pavement preventative maintenance treatment that prevents water intrusion into the pavement base structure.  Cracks occur on the pavement due to traffic loads and thermal stress, and water intrusion then weakens the pavement base structure leading to potholes and pavement failure.  The process includes clearing cracks of vegetation and debris, then applying sealant that is leveled to match the adjacent pavement surface.  This treatment slows the deterioration process of cracks and serves as preparatory work for future pavement resurfacing.

 

The list of roads for this project was developed from the City of Stockton Pavement Management System.  The system analyzes variables such as current pavement condition and projected traffic load to forecast how roadway segments will decline over time.  The forecasts are used to evaluate the cost and benefits of repair options and identify the optimal pavement resurfacing plan.  Roadways with a Pavement Condition Index ranging between 65 and 80 are suitable for this treatment.  Crack sealing the selected roads is anticipated to extend the life of the roadway from two to five years on average.

 

On July 26, 2016, Council adopted a Community Workforce and Training Agreement (CWTA).  The CWTA became effective August 25, 2016, and applies to all Public Works projects over $1 million that are bid after that date.  On July 16, 2019, by Motion No. 2019-07-16-1403, Council extended the CWTA term to August 25, 2024.  The CWTA was not applied to this project because the engineer’s estimate was under $1 million. 

 

Present Situation

 

On June 7, 2024, the Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003, was advertised for bids. On June 27, 2024, six bids were received with the following results:

 

COMPANY NAME                     BID AMOUNT                     ADJUSTED BID AMOUNT

                                          (local preference applied)

Graham Contractors, Inc.

(San Jose, CA)                     $286,000                     $286,000

 

Tally Oil, Inc.

(Madera, CA)                     $341,000                     $341,000

 

Pavement Coatings Co.

(Sacramento, CA)                     $376,400                     $376,400

 

Global Road Sealing, Inc.

(Stanton, CA)                     $380,000                     $380,000

 

The Designs Build, Inc.

(Sacramento, CA)                     $529,333                     $529,333

 

Pavement Rehab Company, Inc.

(Anaheim, CA)                     $583,689                     $583,689

 

Engineer’s Estimate                                          $378,000

 

The requirements of Stockton Municipal Code (SMC) section 3.68.090, Local Business Preference, apply to this project.  Application of the Local Business Preference has no effect on the bid order as all bidders are located outside the City of Stockton and San Joaquin County and are not entitled to a bid preference. The Local Employment Ordinance, SMC section 3.68.095, also applies to this contract. 

 

The bid from Graham Contractors, Inc., the lowest responsive bidder, is regular in all respects and has the proper license to perform the work.  Staff recommends Council approve the plans and specifications for the project and award a Construction Contract to Graham Contractors, Inc. of San Jose, CA, in the amount of $286,000.

 

The project is in conformance with the City’s General Plan, pursuant to California Government Code, section 65402, and is categorically exempt from the requirements of CEQA as specified under Section 15301(c) of the CEQA Guidelines.  As a result, the project has been granted a Categorical Exemption.  The activities related to this project constitute a discretionary project under the City’s jurisdiction and qualifies as a project that does not have a significant effect on the environment.  This resolution will approve the filing of Notice of Exemption No. NOE29-24 under CEQA.  Construction is anticipated to begin late summer 2024 and be completed by fall 2024, weather permitting.

 

FINANCIAL SUMMARY

 

There is sufficient funding available in the Local Street Resurfacing Program FY 2023-24 SB1 - Crack Sealing, Project No. WD24003, to award a Construction Contract to Graham Contractors, Inc. in the amount of $286,000.

 

There is no impact to the City’s General Fund or any other unrestricted fund as a result of taking the recommended actions.

 

Attachment A - Vicinity Map